A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule.
What should the project manager do?

الخيارات

  • A Discuss with the team the need for longer hours to minimize the impact.
  • B Discuss with the project team alternative options to deliver as planned.
  • C Inform the project team that some of them will work for the vendor.
  • D Inform the project team that they may proceed at a more relaxed pace.