A project manager is assigned to work on a large global project. The resources for the project are dispersed among different organizations and countries. After the project kick-off meeting, the project manager learns that many virtual team members are unable to join the regular project update meetings. Their absence will impact the overall project schedule.
What immediate corrective action should the project manager take?

الخيارات

  • A Escalate this issue to the virtual team members' supervisors.
  • B Discuss the issue with the project sponsors and add this as an issue in the issue log.
  • C Discuss the issue with the virtual team members and revise the communications management plan.
  • D Add this issue to the risk management plan and take action if it persists.