اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 21 من 874

كل الأسئلة

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.
What should the project manager do?

الخيارات

  • A Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue.
  • B Delay the project until the issue is addressed and no longer presents as a risk to the project.
  • C Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.
  • D Inform the sponsor that the issue has arisen and that the project's success may be uncertain.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.