A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change.
What should the project manager do?

الخيارات

  • A Ask the new team member to focus only on development and not do the testing.
  • B Request that the new team member do the testing the way it has always been done for this project.
  • C Schedule a meeting with the new team member to learn about the new method of testing.
  • D Coach the new team member to conduct the testing the way it has always been done for this project.