A project to develop an enterprise resource system for a university is in the planning phase. The project has internal stakeholders such as operational departments, students, and academic staff, as well as global stakeholders who receive the information from the university on a regular basis. All the stakeholders have very different expectations and needs from the system.
What should the project manager do to ensure effective communication?

الخيارات

  • A Define communication target groups and provide information, messages, channels, and the frequency of communication for each group.
  • B Ensure all the information about the project implementation is provided to all of the different stakeholders in a unified communication format.
  • C Arrange an information session for all of the stakeholders about the plans for handling their various communication needs.
  • D Plan to implement a united communication platform, where all information about the project will be shared and updated regularly.