A project manager is leading a large-scale project to be deployed in another country, for an external company. After working with the project team, the project manager learns there are many stakeholders from the project manager’s organization, the client organization, and the local community.
What should the project manager do after identifying the stakeholders?

الخيارات

  • A Prioritize the stakeholders that are more interested in the success of the project.
  • B Prioritize stakeholders from the project manager’s own organization.
  • C Prioritize stakeholders from the client’s organization and the local community.
  • D Prioritize the stakeholders that may have more impact on the development of the project.