A team is focusing on quickly developing and shipping new product features due to very aggressive market demands. The team is setting aside long-term work not directly related to the current business objective, which affects product performance and generates more customer support requests.
How can the team minimize the impact of the reduced focus on quality?

الخيارات

  • A Reduce complexity to focus on the minimum viable product (MVP).
  • B Work on the technical debt at a later stage in the project.
  • C Consider implementing test-driven methodology.
  • D Adapt the management plan to reduce the quality constraints.