A project has recently completed its production go-live, meeting the project’s completion requirements in accordance with the scope document. However, the customer has been requesting a number of significant project enhancements.
How should the project manager address the customer’s requests?

الخيارات

  • A Explain to the customer that the project has been completed and enhancements will follow the change management process.
  • B Inform the customer that the project scope is completed and that further enhancements will require the initiation of a new project.
  • C Tell the client that any extra work will require new scoping and pricing before the team can start additional enhancements.
  • D Adjust the project completion requirements to the proposed enhancements and inform the project team of the additional work.