An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.
Which artifact should the project lead use to ensure that the project benefits have been identified?

الخيارات

  • A Product backlog
  • B Statement of work (SOW)
  • C Business case
  • D Solution architecture