During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.
What should the project manager do?

الخيارات

  • A Suggest the team and product manager go with the faster approach, reducing the scope.
  • B Advise the team not to reduce the scope of the feature because the product manager originally included that requirement.
  • C Prepare a presentation for the project sponsor with the team that includes both solutions and seek the sponsor's guidance.
  • D Discuss the issue with the team so the product manager can understand the trade-offs.