اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 435 من 874

كل الأسئلة

A project manager found a repeated defect in a junior developer's code. The code is due in 2 days and a severe fine will be incurred if it is not fixed by then. The project manager wants to reassign the assignment to a more senior developer, but the junior developer is strongly opposed to the reassignment.
What should the project manager do?

الخيارات

  • A Reassign the issue to the senior developer and assign the junior developer to assist in fixing the issue.
  • B Assign the issue to a senior developer and schedule training for the junior developer after the due date.
  • C Reassign the issue to the senior developer after explaining the situation to the junior developer.
  • D Assign the rework to the junior developer after consultation with the senior developer.

النقاشات