A scrum master was recently assigned a newly formed team. How should the scrum master confirm project responsibilities within the team?

الخيارات

  • A Conduct a ways of working (WoW) session to clarify each team member's roles and duties
  • B Assign the team members tasks based upon their competencies and levels of expertise
  • C Consult with senior members of the team to determine the project working standards
  • D Meet with the other teams' scrum masters to ensure that all teams have a standard structure