During execution of the third sprint in a project, a project team is uncertain about the frequent updates on the vendor's platform. The team is concerned about how the updates will impact the rest of the backlog.
What should the project manager do to minimize the uncertainty?

الخيارات

  • A Speak with the vendor and explain that constant updates are impacting the project and request an action plan to minimize the changes.
  • B Explain to the project team that the vendor's updates are something unpredictable, and the team must continue working on the project.
  • C Schedule a retrospective meeting and conduct a risk assessment with the team, implementing mitigation tasks before the next sprint.
  • D Schedule a spike meeting, conduct risk assessments, and incorporate them into the backlog to help with risk mitigation.