A project manager is working on a hybrid project and is responsible for ensuring the design, build, and delivery of the software is completed in an agile way. How should the project manager plan the iteration?

الخيارات

  • A Use a minimum viable product (MVP) to test and discover which features to schedule when and what to fail early.
  • B Use a kanban board as an information radiator to manage work in progress (WIP) at the individual and organizational levels.
  • C Use a work breakdown structure (WBS) with firm start and end dates for all phases to ensure nothing is missed.
  • D Use a product backlog of the functionalities and features required to provide the expected business benefit.