During a project iteration, half of the project team was reallocated to a new project. How should the project lead handle the situation?

الخيارات

  • A Raise the risk of having the velocity impacted for the current iteration and discuss it with the product owner.
  • B Raise the issue with the project stakeholders to analyze the project impact and take the proper actions.
  • C Raise the risk with the project stakeholders and wait until the velocity for the current iteration is calculated.
  • D Raise the issue with the product owner to bring additional resources to the project team.