A feature has been added to the iteration backlog that has been prioritized by the project sponsor over other critical security patches. What should the project manager do?

الخيارات

  • A Perform a risk analysis and then meet with the project sponsor to discuss it.
  • B Give all the work packages parallel priority and continue activities.
  • C Meet with the project sponsor to discuss the feature with the product owner.
  • D Push back on the feature because it is not an immediate priority.