اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 359 من 874

كل الأسئلة

A project manager assembled a team of 10 developers. Because the organization did not have a development team for this project, contractors were hired. In the kick-off meeting, one of the developers recommended the use of development standards. The project manager's previous team in another organization had good development guidelines.
What should the project manager do?

الخيارات

  • A Recommend that the team use industry-accepted guidelines.
  • B Recommend that the team develop their own guidelines.
  • C Contact the previous team and ask for a copy of their guidelines.
  • D Contact the chief information officer (CIO) and request the enterprise development guidelines.