A project is halfway through its execution phase. The quality specifications for the project deliverables are formally accepted. However, a key stakeholder is dissatisfied, stating that the deliverables do not meet the quality specifications.
What should the project manager do in this situation?

الخيارات

  • A Review the requirements traceability matrix and conduct inspections.
  • B Notify the stakeholder that arbitration procedures will be followed.
  • C Document the issue in the issue log and send a report to management.
  • D Inform the project sponsor of the stakeholder's dissatisfaction.