A project manager who is new to an organization observes that an approaching deadline is likely to be missed because there have been some delays on the project due to a lack of resources. What should the project manager do next?

الخيارات

  • A Review the risk management plan to identify the response strategy.
  • B Review the milestone list to determine which tasks can be fast-tracked.
  • C Escalate the issue to the sponsor and debrief them about the situation.
  • D Organize a team meeting to discuss the next course of action.