اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 139 من 874

كل الأسئلة

During the initiating phase of a project, a key stakeholder requests frequent changes to the project scope. What should the project manager do to improve the stakeholder’s engagement?

الخيارات

  • A Discuss the project scope statement with the key stakeholder and build prototypes.
  • B Discuss the work breakdown structure (WBS) with the key stakeholder and refine the requirements.
  • C Update the project backlog and discuss it with the key stakeholder.
  • D Update the project charter and discuss it with the key stakeholder.