اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 138 من 874

كل الأسئلة

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

الخيارات

  • A Project requirements, target benefits, issue log, metrics
  • B Strategic alignment, benefits owner, risk register
  • C Target benefits, benefits owner, lessons learned
  • D Target benefits, strategic alignment, time frame for realizing benefits

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.