اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 128 من 874

كل الأسئلة

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%. During the iteration retrospective, the team realizes that the complexity of the work was underestimated.
What should the project manager do?

الخيارات

  • A Meet with the team to review internal actions to resolve the situation.
  • B Ask to replace some team members with more experienced ones.
  • C Update the issue log and escalate it to the project sponsor.
  • D Ask the technical manager to help the team with the issue.