A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

الخيارات

  • A Check if the changes are covered in the statement of work (SOW).
  • B Determine whether the project team is capable of making the changes.
  • C Review the additional changes and perform integrated change control.
  • D Reject the changes as the lead time is too short.