اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 113 من 874

كل الأسئلة

A company has been following a predictive approach and always waits for the preceding phase to be completed before evaluating the quality of their products. A new project manager with experience in hybrid approaches has been assigned to help increase the efficiency of the company's quality management process.
What should the new project manager do to address the process improvements?

الخيارات

  • A Continue with the process as is, and wait until the next phase to suggest any improvements.
  • B Define a ground rule to comply with the quality standard and ask the team members to apply it.
  • C Discuss the process improvement with the project management office (PMO) lead to update the project delivery framework.
  • D Understand the context and interdependencies of the process from the team members and then define improvements.