During project execution, the project manager observes lower velocity and a high volume of tasks in the testing queue. The project is using a hybrid approach and there are only a few sprints remaining.
What should the project manager do?

الخيارات

  • A Increase the sprint duration so the testing can be completed.
  • B Provide testing training to all the project team members.
  • C Work with the team to understand and solve the issues.
  • D Add a new resource with testing skills to the team.