A hybrid project has just deployed, and the project manager is planning project closure with lessons learned workshops. A key stakeholder informs the project manager that having the Scrum team in the workshops is a waste of time because the project was delivered successfully.
What should the project manager do?

الخيارات

  • A Invite the Scrum team members as optional participants.
  • B Ask the scrum master to attend the workshops.
  • C Invite the Scrum team members as mandatory participants.
  • D Ask the Scrum team members to share retrospectives.