A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion.
What two actions should the project manager take? (Choose 2)

الخيارات

  • A Contact the team member to explain what information can be shared outside the team.
  • B Contact the team member's functional manager and invite them to the next retrospective.
  • C Meet with the product owner to talk about the situation.
  • D Meet with the sponsor to review the situation.
  • E Meet with the entire team to review the ground rules about safe environments.