In the middle of an iteration, an agile team working on the development of a new product was notified that an important team member will leave the project for a few weeks due to some urgent personal issues. What should the project manager do regarding the activities that were the responsibility of this team member?

الخيارات

  • A Reach an agreement with the team on how to handle the situation.
  • B Allow senior management to decide how to proceed with the project.
  • C Reach out to the procurement team to hire a substitute for the team member.
  • D Convince the team member not to leave until the project is completed.