A project is behind schedule because of a delayed equipment installation. This is affecting many other activities. The manager responsible for the equipment delivery notified the project manager that there is a capacity issue for the team doing the installation.
What should the project manager have done to prevent this situation from happening?

الخيارات

  • A Defined the skill requirements more clearly in the scope statement.
  • B Consulted with the installation team on a regular basis to check for conflicts.
  • C Asked the manager to follow the agreed-upon resource management plan.
  • D Conducted periodic reviews with the manager on resource availability.