A company's new communication system will include online dashboard reporting. The executive board might receive bi-weekly performance reports through the online dashboard.
What should the project manager do?

الخيارات

  • A Update the stakeholder engagement plan.
  • B Review the configuration management plan.
  • C Review the project management plan.
  • D Update the communications management plan.