In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration. In the third iteration demo, the marketing team expressed that they need five iterations to launch the product and they have not started yet.
What should the project team have done to avoid this issue?

الخيارات

  • A Scheduled a demo presentation of the product during the first iteration
  • B Held a touchpoint with marketing before the demo to discuss any impediments
  • C Asked the marketing team to start working on the product immediately
  • D Confirmed marketing requirements and constraints when adding to the backlog