السؤال 69 من 874

كل الأسئلة

Several components of an expensive manufacturing project have been returned by the customer... How should the project manager communicate with the customer to help assure them that the project has produced quality products?

الخيارات

  • A Show the customer a sample history of quality.
  • B Show the customer the tolerance and control limits.
  • C Show the customer sample results from the current batch.
  • D Show the customer the quality control measurements.