A project manager is managing a hybrid project... a few stakeholders are reporting that they are unable to find the latest project schedule.
What should the project manager do?

الخيارات

  • A Send the project schedule via email to the stakeholders who need that information.
  • B Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training.
  • C Make sure all stakeholders have access to the system and know where to find project artifacts.
  • D Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively.