اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 60 من 874

كل الأسئلة

During the early phase of a project, the requirements documentation was not approved. It was identified that the leader of a user party was not included in any of the requirements collection communications.
Which of the documents was likely missed or outdated?

الخيارات

  • A Risk Register
  • B Stakeholder Register
  • C Business Documentation
  • D Project Charter

النقاشات