A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.
What should the project manager do next to address this stakeholder’s concerns?

الخيارات

  • A Add the stakeholder to the stakeholder engagement plan.
  • B Review the benefits realization plan with the stakeholder.
  • C Provide the stakeholder with regular updates on project progress.
  • D Review the prior analysis results with the stakeholder.