اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 52 من 874

كل الأسئلة

A real estate developer awards a project to construct three multistoried buildings. The awarded contractor assigns this project to a project manager who starts the work on one building. Three months later, the client informs the project manager that they need only one building and that the other two buildings are not required.

الخيارات

  • A Apply the change management process with the applicable provisions in the contract.
  • B Submit a claim against the real estate developer for the loss of revenue and profits.
  • C Begin construction of all the buildings immediately per the project charter and project management plan.
  • D Continue with the project schedule and escalate the change to the project sponsor.