A project is nearing completion. The contingency time has been consumed. To ensure that the final deliverables are achieved on time and within budget, the project manager has asked the team to follow a rigorous process. This is causing some resistance among the team members.
What should the project manager do to address the growing resistance?

الخيارات

  • A Crash the project schedule and ask project team members to work overtime to meet the new timeline.
  • B Motivate project team members by offering incentives to complete the project on time.
  • C Describe to the team members how specific tools and techniques can be used to finish on time.
  • D Convince team members to use a specific methodology to complete the project on time.