During the implementation of a project, the project team discovered a new opportunity. After an internal review, the project team agreed that the opportunity is outside of the project scope. The project manager decided to update the risk register and escalate the opportunity to a higher level.
What should the project manager do next with this opportunity?

الخيارات

  • A No more action is required.
  • B Share this opportunity with another project.
  • C Further monitor the opportunity.
  • D Establish a contingency reserve to support the opportunity.