At the end of a project with multiple suppliers, the project manager is reviewing the closing process and finds that an unexpected financial balance is remaining. What will help the project manager understand why this has occurred?

الخيارات

  • A Project audit
  • B Procurement audit
  • C Lessons learned
  • D Organizational process assets (OPAs)