اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 44 من 874

كل الأسئلة

During the planning stage of a project the project manager realizes that a standard stakeholder engagement approach will not suffice. One of the client representatives, who is not a key decision maker, is extremely opinionated. This client representative could become a roadblock to progress due to their perceived level of authority during meetings.
How should the project manager handle this moving forward?

الخيارات

  • A Allocate time to gain buy-in from the stakeholder prior to key decision meetings.
  • B Ask that only key decision makers attend the project meetings.
  • C Update the project schedule to cater to this particular stakeholder.
  • D Update the risk register to consider the possible project impacts.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.