An agile project is starting its seventh out of eight iterations. In a planning meeting, the team realizes that an unidentified risk became an issue, and the contingency reserve has to be used.
What should the project manager do?

الخيارات

  • A Help the team review the project approach to initiate the corrective actions.
  • B Ask the sponsor for money to implement the contingency plan.
  • C Ask the team to include the contingency plan in the iteration backlog.
  • D Ask the sponsor to approve inclusion of an additional iteration to the project