Due to organizational changes, several key stakeholders are replaced by new ones in the middle of a project. As a result, numerous new requirements are raised.
What should the project manager do to ensure success of the project?

الخيارات

  • A Emphasize to the new stakeholders that new requirements are not allowed at this stage of the project.
  • B Review and prioritize new requirements with stakeholders to determine which change requests are needed.
  • C Escalate the issue to the project sponsor and seek support to keep the original requirements.
  • D Seek immediate approval to amend the project timeline and budget in order to deliver all new requirements.