A project manager has been assigned to an education project with the objective of training a workforce in application development. One of the deliverables is to provide internships to the best students in the customer's active projects. However, the customer does not have enough projects in progress right now. The project manager decides to create several internal projects in order to ensure the internships.
Which three actions should the project manager take to fulfill this scenario without adding costs for the customer? (Choose 3)

الخيارات

  • A Create a work breakdown structure (WBS) of the new scope with the internal projects.
  • B Create a change request with the scope of the new internal projects.
  • C Manage the quality of the delivery.