A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.
What should the project manager do next?

الخيارات

  • A Proceed with the defined project requirements and delay implementing the new requirements.
  • B Review the new requirements with the compliance department to determine if a change request is needed.
  • C Ignore the new requirements as the current budget and schedule do not allow for any changes.
  • D Add the new requirements to the project scope immediately since they are mandatory changes.