During the execution of a project within an operations function, the project manager encounters scope changes and a delay in the delivery of critical tasks. How should the project manager address this situation?

الخيارات

  • A Communicate the concerns to the project management office (PMO) during the weekly project reports.
  • B Conduct an impact analysis and present the results to the steering committee for approval.
  • C Call for a team meeting to decide if the changes should be included.
  • D Initiate the change request to modify the scope and adjust the timelines.