اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 843 من 874

كل الأسئلة

During the implementation phase of a construction project, the customer asked a key subcontractor to deliver a work package ahead of time. The subcontractor was not prepared for it and asked the project manager for additional budget.
What should the project manager do first?

الخيارات

  • A Submit a change request to accelerate the project as requested.
  • B Ask upper management for more funds, and update the project budget.
  • C Revise the project scope accordingly to cope with the budget changes.
  • D Update the risk register and project log, and manage the budget closely.

النقاشات

لا توجد نقاشات منشورة لهذا السؤال حالياً.