At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

الخيارات

  • A Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.
  • B Review the critical path and update the project schedule with the newly identified tasks.
  • C Defer all actions until the next workshop to keep the team focused on other higher priorities.
  • D Follow up on each item as soon as possible to ensure timely completion and report the status to management.