A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

الخيارات

  • A Allow the project team to decide what is the most appropriate requirement to follow.
  • B Negotiate a common agreement with the involved stakeholders regarding the requirements.
  • C Prioritize other items for the team and deal with the conflicting requirements later.
  • D Escalate to the project management office (PMO) and request a solution for the requirements.