اختبار شهادة إدارة المشاريع Project Management Professional (PMP)

السؤال 838 من 874

كل الأسئلة

A project manager is managing an innovation project for a big corporation. The project manager is planning to use email as the main communication channel; however, the product owner prefers to use another approved communication tool instead of email.
What should the project manager do?

الخيارات

  • A Suggest to the team to start using the communication tool suggested by the product owner.
  • B Request the product owner to use email because using another tool will increase the workload.
  • C Update the communications management plan based on the product owner's preferences and distribute to the team.
  • D Contact the sponsor to request direction regarding the communication tool to be used by the project team.