A town wants to build a community center and has appointed a project manager. A site was found, and all of the necessary approvals and governance were completed. When the project kick-off was held, it was discovered that a local farmers' group was not consulted, and they use the site for a monthly market.
What should the project manager do to move forward with the project?

الخيارات

  • A Document a risk related to the impact that the farmers' group could bring to the project.
  • B Request that the project sponsor discuss compensation with the farmers' group for the lost business.
  • C Discuss the project objectives with all stakeholders, including the farmers' group, and review their requirements.
  • D Continue building the center as the farmers' group does not need to be consulted.